Now rising
on the lake
Building Progress
One Lady Bird Lake is rising with the same care and dedication that shaped its design.
Timeline
Milestone
by Milestone
Aug 2025
Groundbreaking
Official groundbreaking marks the start of construction on One Lade Bird Lake.
Jan 2026
Foundation
Finished foundation wall and started mass excavation.
Apr 2026
Ground Level Concrete Pour
Sep 2026
Exterior window and facade installation begins
Oct 2026
Progress continues
Progress continues on the exterior façade, windows, and height of the building as we reach the 11th floor.